Ayala High School Cement Treatment

Chino Hills, CA

In late 2020, the Restructuring team in Jurupa Valley performed soil stabilization at Ayala High School in Chino Hills, CA who were having pumping subgrade issues at their outdoor basketball courts. Partnering with Premier Paving, the team completed over 55,000 SF of cement treat at 5% cement and 12” in depth. Overall, we helped the school district and Premier Paving save money by treating existing material rather than removing the existing non-suitable material by bringing in rock base, not to mention the numerous environmental benefits that come from treating in-place. Amazing job to everyone involved including Cody Spetz, Lawrence Reagins, Robert Almind, Joshua Guenther!